Procurement programmes
Supplier risk
Selected
Tejas Mk1A — Tranche 2 (97 aircraft)
₹41,800 of 65,000 cr · vendor HAL
MDL / TKMS82
14 delayed · Tech-transfer impasse
DRDO / CABS71
9 delayed · Platform supply gap
Almaz-Antey66
7 delayed · Component sub-vendor risk
HAL52
11 delayed · Engine bottleneck (GE-F404)
BDL / DRDO41
3 delayed · Minor schedule slip
L&T Defence28
1 delayed · Healthy
Boeing22
0 delayed · On plan
Solar / EEL18
0 delayed · On plan